"Peanut", the framing engineer, guides the hose from the concrete pump.



The trenches are ready for concrete.



The concrete trucks dump their concrete into the pumper truck. They started pouring at 6:30 a.m. and finished around 9:00 a.m.



Ronnie Bogard, the builder, on the left and "Peanut" (George Carroll), the framer, on the right.



The concrete pump in action.



Setting rebar into the fresh concrete for the cinder block chain wall to come. The chain wall will be the form for the slab.



Peanut gets a helping hand over the freshly poured trench.



The footers are complete; the strings are at the height of the slab.