The second floor starts to get sheathing.

The 2x4 boards are used to true up the walls in preparation for the trusses for the floor above.

Trusses get installed over the dining room.

The second floor balcony is now installed.

These are the windows for the second floor hollywood style bath.

Here's another view of trusses being installed over the dining room.

Here's a shot of the living room from the front porch.

The dining room is in the foreground with the kitchen beyond.

Notice the water on the kitchen floor due to recent rain.

The kitchen stairs down to the garage will stay treated lumber due to the possiblity of flooding.

The underside of the second floor balcony.

The treated lumber supports for the second floor balcony are attached to a 2x4 treated ledge.

This is the repair to one of the errors the architect made in the first floor framing plan. The bedroom wall is over the heavy
plywood beam you see installed here. The trusses originally went to the cinder block wall, but that would have put the bedroom wall into the middle of
the living room window.